Walgreens on Magazine – Update 11/2/12
The project is still moving along at a fast pace. Following the setting of the base cast stone, you can now see that the front façade brick veneer is going up quickly. The large windows facing Magazine street are taking shape and it will not be long before this phase is complete. The interior work is progressing with the installation of drywall, completion of framing, HVAC Ductwork, Electrical Rough-In and the concrete decking work at the second floor.