Mid-City Market – December Update
We have moved forward rapidly in the site and building construction at Mid-City Market in New Orleans. At Winn-Dixie, structural steel arrived on site and we have erected the standing up columns and joist girders within the interior footprint of the 53,000 square-foot building. We have completed underground plumbing and electrical work in all the areas with the steel overhead. In the next two weeks, we will be constructing the exterior load bearing metal stud framing walls and following immediately thereafter will be structural steel at the exterior. We will be completing underground plumbing and electrical work in exterior areas within two weeks, and beginning concrete pours of the slab at Winn-Dixie on December 21st.
At the existing building under renovation, we have erected the steel tower elements for the entrances of the stores which will include Office Depot, Jefferson Feed, Panera, and Pizza Hut. The changes to the rear wall and repairs for the masonry are approximately 90% completed, and within the next two weeks the front curbs for the storefronts will be poured. We have begun the prep work and plan for the repairs for the roofing and decking to be replaced as well. The two small-shop buildings fronting Carrollton are progressing quickly as well – we are progressing with the underground work, expecting structural steel on site within the next two weeks, and aim to complete the slab pours by the end of the year.
Walgreens on Magazine – Update 12/6/12
Both interior and exterior work are progressing at a good pace this month. As the photo indicates the address precast stone was placed at the roofline just this week and the brick veneer on Magazine Street is nearly complete. This will be striking when the scaffolding is removed and when all the fine stucco detail work is complete in the next few weeks. Interior work is a combination of drywall installation, initial floor prep, electrical rough-in and final HVAC ductwork connections. The rear wall facing the parking lot is now covered with stucco and will have the finish coat in place this coming week. Things are coming together, stay tuned.
Walgreens on Magazine – Update 11/2/12
The project is still moving along at a fast pace. Following the setting of the base cast stone, you can now see that the front façade brick veneer is going up quickly. The large windows facing Magazine street are taking shape and it will not be long before this phase is complete. The interior work is progressing with the installation of drywall, completion of framing, HVAC Ductwork, Electrical Rough-In and the concrete decking work at the second floor.
[wpvideo 8M96EzrP]Walgreens on Magazine – Update 10/25/12
Things are moving fast at Magazine Street Walgreens. We now have laid the starting course of cast stone on the front elevation, from there on up we will see the brick veneer going up which will help define the window openings. The roofing is now complete, building totally dried in and HVAC Units are in place. Ductwork is now underway inside as well as a flurry of activity of Drywall Studwork, Electrical Rough-in and some of the remaining selective demolishing work. The Walgreens specified tile flooring is being manufactured and due to ship from Italy in early December, this store will not look like your typical Walgreens….we can’t wait to see it either!
Walgreens on Magazine – Update 10/15/12
The Magazine Street Walgreens project is really taking shape, the great weather has allowed the roofing to be completed as well as the final topping out of the new rear wall. The front façade stone and brick were delivered last week, and final touches on the front were done to allow the veneer to start today, Monday October 15th. Interior progress is moving along at a fast pace, drywall framing, sprinkler rough in, electrical and plumbing rough in work is happening just about everywhere you look.